You should be addressing the following resources:

  • Yard layout and fabrication capacity by size and tonnage
  • Gantry cranes, overhead cranes, mobile cranes
  • Office space
  • Assembly areas
  • Major construction equipment inventory
  • Shop layouts, capacity and equipment lists
  • Covered and specialized work areas
  • Bulkhead size and capacity
  • Quay side capacity and barge draft capacity load out capacity across quayside and bulkhead
  • Access to open water
  • Vessel movement restrictions
  • Warehousing and material storage areas
  • Lofting facilities
  • NDE services

2
AngelPenavega 5 years ago

You may need to consider the followings in your Fabrication Execution Plan:

  • List of frabrication work sites
  • Manpower requirements
  • Describe which items will be fabricated at each work site
  • Describe plan for setting up facilities required before commencing fabrication activities
  • Describe how fabrication at multiple work sites will be coordinated
  • Fabrication schedule with milestones
  • Consider late arriving equipment and materials on the fabrication sequence and critical path
  • Consider accommodation and office spaces
  • Consider work areas (shops) needed for fabrication activities for fit-up, welding, blasting and painting
  • Consider interfaces between fabrication work sites
  • Define for each construction site the fabrication, equipment, and transportation capacity

1
AngelPenavega 5 years ago

By the way, here are some of the resources for Installation:

  • Vessel name and layout
  • Age
  • Class and certificate authority
  • Capacity (lift, launch, transport, speed)
  • Survey Equipment/spread
  • Accommodations
  • Pile Driving hammers
  • Survey equipment
  • Diving/ROV spreads
  • Office space
  • Communications
  • Conference and assemply areas
  • Rigging and welding construction equipment inventory

Related Posts


Required Documentation for Vessel Construction, Alteration and Repair
Required Documentation for Vessel Construction, Alteration and Repair

All work should be performed per the requirements of the latest version of ASME Section VIII Div. 1, API-510 and …

Installation Workover Control System (IWOCS) for Conventional Guideline Subsea Completion Equipment
Installation Workover Control System (IWOCS) for Conventional Guideline Subsea Completion Equipment

1.0 ScopeThis specification defines the minimum requirements to cover the procurement of an electro hydraulic installation and workover control system …

Steel Line Pipe for Gas and Liquid Pipelines for Offshore Applications
Steel Line Pipe for Gas and Liquid Pipelines for Offshore Applications

1.0 ScopeThis Specification defines the requirements for manufacturing, testing, inspecting, marking, and shipping of steel line pipe for gas and …