Specifications and requirements for subsea hydraulic system cleanliness?

Asked by bbenoit 5 years, 8 months ago | 2 Answers

Can someone please share the common specifications and requirements for subsea hydraulic system cleanliness?


2 Answers

3
jcargill 5 years, 8 months ago

All subsea valves associated with or controlled by the subsea control system and/or IWOCS should:

  • Be designed and manufactured to attain, as a minimum, a hydraulic cleanliness level meeting SAE AS 4059D Class 6 B-F requirements through factory acceptance testing.  Class 8 is the minimum level of cleanliness during Systems Integration Testing (SIT) and offshore work.
  • Be capable of maintaining a Class 8 level of cleanliness during subsea operations throughout the expected field life.
  • Be designed and qualified to operate properly even if the fluid cleanliness drops to Class 12 throughout the design life.  The Subsea Control Module (SCM) filter should be capable of operating at Class 8 for the design life.
  • Be assembled clean and should not rely on flushing after assembly to obtain the Class 6 cleanliness level.  Cleaning operations to be performed should include demagnetizing, vibration, cleaning in ultrasonic bath, clean room assembly and flushing.
  • Include provisions to circulate hydraulic fluid through the system for purging air/flushing and taking fluid samples.
  • Be designed to eliminate air traps and to facilitate flushing.
  • Be certified by the microscope method.

2
kmoretz 5 years, 8 months ago
Fluids received in drums should be cleaned to Class 6 prior to use in any hydraulically operated permanent or running tool equipment. Circuits for running tools and those operated exclusively by ROV hot stab should be cleaned to Class 8. You can refer to Appendix of ISO 13628-6 Properties and Testing of Control Fluids for further information.

Related Posts


Subsea Controls Umbilical Distribution Configuration
Subsea Controls Umbilical Distribution Configuration

PURPOSEAs part of any Pre-FEED or FEED studies, the configuration of the subsea distribution equipment should be defined in the …

Application of Thermal Sprayed Aluminum to Subsea Structures
Application of Thermal Sprayed Aluminum to Subsea Structures

1.0 ScopeThis specification defines the minimum requirements for the surface preparation, application and inspection of thermal sprayed aluminum (TSA) coatings …

Subsea Umbilical, Controls Testing and Pre-Commissioning Requirements
Subsea Umbilical, Controls Testing and Pre-Commissioning Requirements

1. INTRODUCTION1.1 Project OverviewThis document provides the requirements for testing and commissioning of the umbilicals and subsea production controls system.1.2 …

Subsea Commissioning Philosophy
Subsea Commissioning Philosophy

This document is to detail pre-commissioning, commissioning, start-up and performance testing requirements for the subsea system.Drilling and Completion activities related …

Subsea DeCommissioning Philosophy
Subsea DeCommissioning Philosophy

This document is to detail the requirements for decommissioning of the subsea systems, flowlines and wells.Wells, subsea and flowline systems …

Subsea Sparing and Tooling Philosophy
Subsea Sparing and Tooling Philosophy

This document is to describe the sparing and tooling requirements for the manufacture, testing, installation, pre-commissioning, commissioning and operation of …