Can someone describe the FPSO offloading operation that involves a buoy?


1 Answer

3
Normandy 5 years, 11 months ago

The Catenary Anchor Leg Mooring (CALM) buoy is typically moored a distance (approximately) 2 km away from the FPSO, downwind of the FPSO. The export tanker will be approaching the buoy opposite the FPSO and will be assisted by one or more tugs.

During the approach, the assisting tug is connected to the export tanker to ensure it stops. When the export tanker is in position and stable, the tug will go to the forward and connect the hawser between the buoy and the tanker, and subsequently the floating hose. Hereafter, the tug will be on stand-by for connection for hold-back or disconnection operations.

Related Posts


Material Selection and Corrosion Control for Offshore Platform and FPSO
Material Selection and Corrosion Control for Offshore Platform and FPSO

Detailed corrosion prediction evaluations including consideration for CO2 should be performed to establish a materials selection and corrosion control report …

Next generation new built hulls for Floating Production Storage and Offloading (FPSO)
Next generation new built hulls for Floating Production Storage and Offloading (FPSO)

MODEC has announced that it has developed the “MODEC NOAH” and “M350”, next generation new built hulls for Floating Production …

FPSO Conversion Lessons Learned
FPSO Conversion Lessons Learned

FPSO conversions! Either VLCC to FPSO, FPSO redeployment, or similar engineering works for life extension of naval surface vessels, this …