Should Fire Water Pumps be sized to provide water to the single largest credible fire scenario (both for cooling, e.g. deluge and for fire-fighting, foam generation) including escape routes.

The followings are being considered:

  • The deluge systems should be able to provide protection to the FPSO topside process areas and all escape routes and stairways. 
  • Release of deluge in any fire zone should automatically initiate the release of deluge on the associated platform escape routes.


1 Answer

0
wozniakmic 5 years, 10 months ago
It is not typical to include firewater pump sizing to provide deluge for escape routes. Firewater pump sizing should be detailed in EPC Company's Active Fire Protection Philosophy and Fire Zone Philosophy. Deluge on escape routes poses an increased safety risk for personnel attempting to use those escape routes by hindering visibility and creating additional slipping hazards. The design should provide for sufficient escape routes and redundancy to allow safe egress and access to any event area without need for deluge. Maintaining the requirement for deluge on escape routes will not only have a negative impact on safety, it will also have a cost increase.

Related Posts


Material Selection and Corrosion Control for Offshore Platform and FPSO
Material Selection and Corrosion Control for Offshore Platform and FPSO

Detailed corrosion prediction evaluations including consideration for CO2 should be performed to establish a materials selection and corrosion control report …

Solubility of inert gasses in water
Solubility of inert gasses in water

Solubility charts of following inert gasses in Water at Atmospheric Pressure (101.3kPa) are shown below: Gas Name Formula Molecular Weight …

Next generation new built hulls for Floating Production Storage and Offloading (FPSO)
Next generation new built hulls for Floating Production Storage and Offloading (FPSO)

MODEC has announced that it has developed the “MODEC NOAH” and “M350”, next generation new built hulls for Floating Production …

FPSO Conversion Lessons Learned
FPSO Conversion Lessons Learned

FPSO conversions! Either VLCC to FPSO, FPSO redeployment, or similar engineering works for life extension of naval surface vessels, this …