Does FPSO Contractor perform a pre‐installation ROV survey of the seabed where the Mooring legs will be installed?

Asked by RichS29 5 years, 12 months ago | 1 Answers

Does FPSO Contractor perform a pre‐installation ROV survey of the seabed in the vicinity of the positions at which the Mooring legs (piles and lines) will be installed and wet stored?


1 Answer

0
gagonza 5 years, 12 months ago
Yes, the FPSO Contractor should perform a pre‐installation ROV survey of the seabed in the vicinity of the positions at which the Mooring legs (piles and lines) will be installed and wet stored. The Mooring legs deployment will be performed in continuity of this pre‐installation ROV survey (same offshore campaign). Debris removal or cleaning of site (no obstruction on abandonment corridor) may or may not be included.